23.12 Carrying out final maintenance work

Building Technologies
Fire Safety
Activity
Check the function of the delay times t1 and t2.
Activate a global alarm with an 'Automatic detector' in the
'Unmanned operation' operation mode.
Activate a local and global alarm by setting a 'Manual call point' to
the 'Manned operation' and 'Unmanned operation' operation
modes.
Check automatic switchover from 'Manned operation' to
'Unmanned operation' on the basis of the event memory entries.
Check activation of the remote transmission equipment with
'ALARM'.
Table 7: Intervals for the function test
Activity
Check the ↑ effects of the outputs owned by the customer. Arrange
a time with the customer.
Triggering of the outputs. You will find information on testing the
outputs in document 'A6V10211076'.
Table 8: Intervals for the extinguishing function test
1. Activate a test alarm through the system operator with remote transmission.
2. Issue subsequent instructions if necessary.
3. Ensure that the system file is available and up to date.
4. Update the system data when the central configuration is changed. Archive a
copy with the ↑ 'Site' and a copy in the office.
5. Check the master data sheet (phone no., contact person, etc.).
6. Replace all used material.
7. Cancel all blockings and 'OFF' statuses.
8. Have the revision confirmed by the system owner.
Maintenance
Carrying out final maintenance work
A6V10210416_j_en_--
23
Interval
(years)
1
2
5
X
X
X
X
X
Interval
(years)
1
2
5
X
X
153 | 178
2018-08-29

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents