Figure 2-9 Primary Contactor Test Points - Henny Penny 500 Service Manual

4-head electric pressure fryers
Hide thumbs Also See for 500:
Table of Contents

Advertisement

Remove electrical power supplied to the fryer.
1 1 ) )
Remove the control panel and insert it in the slot above the door, see
2 2 ) )
the Control , page
14.
Perform a check on the contactor as follows:
3 3 ) )
from 23 to 29
from 24 to 28
from 25 to 27
from 30 to 34
from 31 to 35
from 32 to 36
from 22 to 26
from 33 to 37
See
Figure 2-9 Primary Contactor Test Points , page 33
Contactor Test Points , page 34

Figure 2-9 Primary Contactor Test Points

Test Points
open circuit
open circuit
open circuit
open circuit
open circuit
open circuit
ohm reading 415
ohm reading 415
for test point locations.
2.4 Lower
Results
and
Figure 2-10 Heat
33