Chapter 6 – Maintenance
Test Setup
6.3.5.4
1. Connect the test equipment to the unit under test as
2. Power up the Equipment Under Test (EUT)
3. Press STATUS context key and insure battery voltage
4. Configure the 8904 as follows:
Honeywell Confidential: Use or disclosure of information on this page is subject to the restrictions on the title page.
Procedure:
depicted in Figure 1.
reported is >3.5 Vdc.
Channels 1 and 2 Float OFF,
Channel 1 19 mV, 40 Hz, Phase 0 deg, Sinewave,
Channel 2 1V, 40 Hz, Phase 180 deg, Squarewave,
13841 Rev A
220