R e p l a c i n g M a j o r C o m p o n e n t s
5. Connect the wires identified in the table and photo below.
6. Replace the water tank access panel.
a) Slide the rear of the access panel into the area around the rear of the tank. The metal top of the
machine behind the tank has to slide into the notches on the sides at the rear of the access panel.
b) Connect the ground wire (#13-3) to the grounding tab on the inside front of the access panel.
CAFFÈ MIO – OPERATION AND SERVICE
S E C T I O N
#1-2
WIRE #
CONNECTED TO:
#11-2
Heater element
#14
Thermal cut-off switch
#1-2
Level probe - long
#4-3
Level probe - long
#5-2
Level probe - short