Checklist For Commissioning - Festo CTEU-DN Description, Functions And Maintenance

Universal bus node
Table of Contents

Advertisement

4. Commissioning
4.4

Checklist for commissioning

Festo P.BE-CTEU-DN-OP+MAINT-EN en 1206NH
Observance of the following points helps you to avoid errors
during commissioning on DeviceNet.
Finally check the DIL switch settings again.
Check the address assignment of the inputs and outputs.
Check the configured address range (process data and
assigned input and output bytes).
Test the inputs and outputs if necessary.
Check the parameterisation, via the configuration pro-
gram for example.
Make sure that the desired parameterisation is restored
after a restart or after fieldbus interruptions.
4-19