3. Preparing for commissioning

3.1.2 Prerequisites for commissioning

3-4
Installation of the CTEU-DN bus node complete
Note
Information on installing and mounting and the basic
setting for the bus node can be found in the description
"Universal bus node CTEU-DN – Installation and
interfaces" (P.BE-CTEU-DN-INSTALL, Part 1 of the product
documentation on the bus node):
www.festo.com
Anwenderdokumentation (Techn. Dokumentation).
Make sure that the DIL switches of the bus node are set
correctly.
Basic setting for fieldbus communication checked:
DeviceNet address or station number
Baud rate
Optional settings checked:
Diagnostics
Fail state and idle mode
Make sure that all DeviceNet connecting cables are con-
nected and checked:
Host system (controller) and bus node connected to
the network
Network connections checked