Procedure 43
Testing the superloops and the fiber-optic link
Step
1
2
3
4
Copyright © 2007-2009 Nortel Networks
.
Action
To disable all superloops to be tested, place the MMI terminal
into the Host SDI mode:
FII::>HO
Enter Password:> HOST (all caps)
At the prompt, type LD 32 and press the Enter key to access
the overlay. Then execute the DISL sl command for each
superloop, where sl is the superloop number.
Place the MMI terminal into the MMI mode by entering @@@.
To test the disabled superloop and the fiber-optic link, execute
the T A command at the MMI terminal.
Run the test once by typing 0 or run the test for a number of
minutes from 1 to 98 by typing the number of minutes. By typing
99, the test runs continuously until stopped.
Stop the test by typing S.
Example:
FII::>T A
Enter Duration of Test (1-98 Mins, 0= Once,
99= Forever)
Verify Super Loops are Disabled. Hit Q to
quit or any Key to Cont
Link 1 PASSED
Link 2 PASSED
Link 3 PASSED
Link 4 PASSED
Link 5 PASSED
Link 6 PASSED
Link 7 PASSED
Link 8 PASSED
DS-30 Link Test Completed
DS-30A Frame 1 PASSED
DS-30A Frame 2 PASSED
DS-30A Frame Test Completed
DS-30A Clock 1 PASSED
DS-30A Clock 2 PASSED
DS-30A Clock Test Completed
Nortel Communication Server 1000
Fiber Remote Multi-IPE Interface Fundamentals
NN43021-556 03.01
11 May 2009
Remote IPE fault isolation and correction 137

Advertisement

Table of Contents
loading

This manual is also suitable for:

Communication server 1000e cp piiCommunication server 1000e cp pivCommunication server 1000e cp pmCommunication server 1000m single group cp piiCommunication server 1000m single group cp pivCommunication server 1000m multi group cp pii ... Show all

Table of Contents