Parts installation in a Passport 15000 in a NEBS 2000 frame
Prerequisites to parts installation in a Passport 15000 in a
NEBS 2000 frame
Parts installation in a Passport 15000 in a NEBS 2000 frame
task flow
Passport 15000, 20000 Hardware Installation, Maintenance, and Upgrade
Install the parts of a Passport 15000 that is mounted in a NEBS 2000 frame
to enable the switch to be put into service.
•
"Prerequisites to parts installation in a Passport 15000 in a NEBS 2000
frame" (page 165)
•
"Parts installation in a Passport 15000 in a NEBS 2000 frame task flow"
(page 165)
•
The NEBS 2000 frame must already be installed as indicated by "NEBS
2000 frame installation" (page 161).
•
Power and ground cables must be routed to the planned location of the
Passport prior to beginning this task. See the 241-1501-205 Passport
15000, 20000 Site Requirements and Preparation Guide.
This task flow shows the sequence of procedures you do to install the parts of
a Passport 15000 that is mounted in a NEBS 2000 frame. To link to any
procedure, go to "Task flow navigation" (page 167).
Chapter 11 Initial switch hardware installations 165
5.2S2