Chapter 7
Cooling units
Passport 15000, 20000 Hardware Installation, Maintenance, and Upgrade
Select from the following tasks and procedures:
•
"Cooling unit replacement" (page 100)
•
"Fan controller replacement" (page 102)
•
"Fan replacement" (page 104)
•
"Replacing a cooling unit alarm cable" (page 787)
•
"Replacing a cooling unit power cable" (page 789)
•
"Replacing an air filter" (page 800)
•
"Temperature sensor replacement" (page 106)
•
"Temperature sensor bracket assembly replacement" (page 109)
When you have a cooling unit to install, see the task flow "Installation of a
second switch into a NEBS 2000 frame" (page 156) or "Passport 15000 or
20000 switch installation into an EIA rack" (page 173).
99
5.2S2