210 Chapter 14 Power-and-ground hardware of a Passport 15000 or 20000
Powerup of a Passport 15000 or 20000
Prerequisites to powerup of a Passport 15000 or 20000
241-1501-240 5.2S2
Power up a Passport 15000 or 20000 to enable the switch hardware to be
downloaded with software for initial operation or to return the system to
operation.
•
"Prerequisites to powerup of a Passport 15000 or 20000" (page 210)
•
"Powerup of a Passport 15000 or 20000 task flow" (page 211)
•
You need access to 241-5701-270 Passport 7400, 15000, 20000 Software
Installation Guide.
•
All cables must be installed for interworking equipment, signalling
(traffic), timing, and alarms.
•
All power cables must be installed from the breaker interface panel (BIP)
up to the power source without being connected and must have passed the
checks with the power off.
•
All equipment that is connected to or interworking with the
Passport 15000 or 20000 must share the same site ground window.
•
Each Passport sparing panel will be powered up from the function
processor (FP) cards through the control port cable when at least one FP
is powered up.
•
The following interworking equipment can be powered up independently
from the BIP, but needs to be on to verify operation of the system:
— an EdgeLink 100 DS3 multiplexor
— the hardware of a Preside Multiservice Data Manager (MDM)
— a local operator terminal and its modem (if present)
— a multiport aggregate device
— the Passport 7400 of a Passport 15000-VSS
— a Shasta 5000 that shares a NEBS 2000 frame with a Passport 15000
or 20000