Step
9
Reverse the procedure to install the new pump.
CO
S
S
HUTOFF
OLENOID
2
The CO2 shutoff valves and solenoids, shown in Figure 73, are located near the center of the unit and are mounted on a
bracket to the bottom of the chassis. They control the injection of CO2 with the syrup/water combination to provide the
final mixture for the product. There are one of these solenoids for each barrel in the system. When working in this area,
care should be taken not to damage or misalign the CO2 metering orifice. To replace one of these solenoids, perform the
procedure in Table 76.
CO
Metering
Orifice
!
WARNING:
In Step 1, disconnect electrical power from the unit. Failure to disconnect the power could result in serious injury, death, or
equipment damage.
Step
Action
1
Disconnect power from the unit.
2
Disconnect the CO2 supply from the unit.
3
Remove the rear cover and side panels.
Carefully remove the tubing from the right-angle fitting at the rear of the valve. Be
4
sure not to damage the CO2 metering orifice located above the fitting (Figure 73).
5
Remove the tubing from the front of the valve.
6
Remove the two (2) locknuts mounting the valve and solenoid to the base.
7
Remove the two (2) mounting screws from the bottom of the mounting bracket.
8
Replace the valve and solenoid.
9
Reverse the procedure to reinstall the valve and solenoid into the unit.
10
Test the unit for CO2 leaks.
11
Replace the rear and side panels.
12
Reconnect power to the unit.
© 2022, Marmon Foodservice Technologies Inc.
R
EPLACEMENT
2
CO
2
Shutoff
Solenoid
Figure 73. Side View of CO
- 91 -
Viper Installation, Service & Decommissioning Manual
Table 75
Action
Shutoff Solenoid (2 Barrel Unit)
2
Table 76
CO
2
Shutoff
Valve
Publication Number: 620073146SER

Advertisement

Table of Contents
loading

This manual is also suitable for:

R-454c

Table of Contents