Fill Screen
Screen
Fill
Fill
Screen
NOTE:
NOTE:
NOTE: This screen is visible only if Manual Override
is enabled on
System Screen 1, page
The Fill screen displays the following information for
the pump assigned to the current color:
• Material. Select Color (A), Catalyst (B), or Solvent.
The pump animation at the top of the screen will
show the selected material.
• Flush Line (only for systems with color change).
Select this box if you want to flush the specified
material line. The system uses flush sequence 1.
NOTE: Use the toggle softkey to switch between Mix
NOTE:
NOTE:
Units.
To prime the pumps and fill the lines, first read
Prime and Fill the System, page
1. Press the Edit softkey
for editing.
2. Select Color (A).
3. If the selected material is not already loaded,
press the Prime softkey
prime Color (A) into the selected pump through
the selected color valve and out the outlet dump
valve.
4. Press the Fill softkey
attempt to fill the Color (A) lines until the user
presses Stop
container.
5. Repeat for Catalyst (B).
Figure 24 Fill Screen, Color (A) Selected
3A4486D
68.
20.
to open the screen
. The system will
. The system will
. Trigger the gun into a waste
Figure 25 Fill Screen, Solvent Selected
Pre-Fill Pump
Pump
Pre-Fill
Pre-Fill
Pump
The pump pre-fill option is available for pumps that
have color change, but only a single material (color or
catalyst). The pre-fill option may be used for pumps
that remain filled with material when the system was
powered down.
Press the Pre-Fill softkey
pump without flushing or expelling any material
unnecessarily.
Figure 26 Fill Screen, Pre-Fill Option
Run Mode Screens
to "prime" the