Clearance Requirements for Airflow and Hardware Maintenance on MX104 Routers
Related
Documentation
Copyright © 2017, Juniper Networks, Inc.
When planning the installation site, allow sufficient clearance around the rack (see
Figure 19 on page
75):
For the cooling system to function properly, the airflow around the chassis must be
unrestricted. Allow at least 6 in. (15.2 cm) of clearance between side-cooled routers.
Allow 2.8 in. (7 cm) between the side of the chassis and any non-heat-producing
surface such as a wall.
For service personnel to remove and install hardware components, there must be
adequate space at the front and back of the router. At least 24 in. (61 cm) is required
both in front of and behind the router. NEBS GR-63 recommends that you allow at
least 30 in. (72.6 cm) in front of the rack and 24 in. (61.0 cm) behind the router.

Figure 19: MX104 Chassis Dimensions and Clearance Requirements

Preparing the Site for the MX104 Router Overview on page 71
Rack Requirements for MX104 Routers on page 72
Cabinet Requirements for MX104 Routers on page 73
Installing and Connecting an MX104 Router Overview on page 109