Clearance Requirements for Airflow and Hardware Maintenance of
ACX7348 Routers
When planning the site for installing an ACX7348 router, you must allow sufficient clearance around the
installed chassis. See
Figure 21 on page
Figure 21: Clearance Requirements for Hardware Maintenance of ACX7348 Routers
Ensure that your installation of the ACX7348 router chassis meets the following requirements:
• For the cooling system to function properly, the airflow around the chassis must be unrestricted. See
"Airflow" on page 19
• If you are mounting an ACX7348 router in a rack or cabinet with other equipment, ensure that the
exhaust from other equipment does not blow into the intake vents of the chassis.
• For service personnel to remove and install hardware components, and to accommodate the
interface and power cable bend radius, allow at least 24 in. (61 cm) of space both at the front and the
rear of the router.
47.
for more information about the airflow through the chassis.