Table 35: MX5, MX10, MX40, and MX80 Rack Requirements and Specifications (continued)
Rack Requirement
Rack connection to the building
structure
MX5, MX10, MX40, and MX80 Routers Clearance Requirements for Airflow and Hardware
Maintenance
Copyright © 2019, Juniper Networks, Inc.
Guidelines
Secure the rack to the building structure.
If earthquakes are a possibility in your geographic area, secure the rack to the floor.
Secure the rack to the ceiling brackets as well as wall or floor brackets for maximum
stability.
Figure 25: Typical Open-Frame Rack
When planning the installation site, allow sufficient clearance around the rack (see
Figure 26 on page
66):
For the cooling system to function properly, the airflow around the chassis must be
unrestricted. Allow at least 6 in. (15.2 cm) of clearance between side-cooled routers.
Allow 2.8 in. (7 cm) between the side of the chassis and any non-heat-producing
surface such as a wall.
Chapter 2: Site Planning, Preparation, and Specifications
65