Section 2: Installation and Setup
To create this loop, connect the OUT/warm and IN/
cool hoses (Figure 2-15), as described below (hose
connections may not be labeled). Make sure to
depress each hose connector tab before inserting the
hose end, then release to seal. This prevents damage
caused by forcing the gasket end into a closed
connector.
• The long loose hose connected to the reservoir is
the OUT/warm hose from the projection head-con-
nect to the projection head location closest to the
non-operator's side of the projector.
• The short loose hose connected to the heat
exchanger is the IN/cool hose-connect to the pro-
jector head location closest to the operator's side of
the projector.
IMPORTANT! To prevent damage to the sealing gasket, always depress the connector tab when
inserting the hose end. Avoid "forcing" together and listen for "click".

FILL THE RESERVOIR COMPLETELY (INITIAL FILLING FOR HOSES ONLY)

After connecting the hoses, completely fill the cooler reservoir with Christie's 50/50 mix of distilled
water and ethylene glycol (Figure 2-16).
For this first filling, simply fill the reservoir completely. There is no need to check the gauge. Virtually
all of this first supply of liquid will be drained into the hoses upon initial power-up, at which point the
reservoir must be re-filled to the correct level at the gauge window.
2-10
F
2-16 F
R
IGURE
ILL
ESERVOIR
F
2-15 C
IGURE
ONNECTING
CP2000 Setup Guide
020-100070-01 Rev. 1 (10/08)
H
OSES

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents