Verifying the installation

WARNING!
An S12508 has one power switch, and an S12518 has two power switches. Make sure that you have
turned off the power before checking the installation to avoid bodily injury and switch damage.
After the installation is completed, verify the installation against the following list. Be sure that all check
results are positive.
Table 13 Installation checklist
Item
The grounding cable is correctly grounded.
Fan trays are correctly installed and make close contact
with the backplane.
Power modules are correctly installed and have close
contact with the frames.
The power switch is off (the power switch is at the OFF
position).
Power cords are correctly connected.
MPUs are correctly installed and have close contact with
the backplane.
Line cards are correctly installed and have close contact
with the backplane.
Switching fabric modules are correctly installed and have
close contact with the backplane.
Result
Yes
No
44
Remarks