4 Parts Replacement
17. Install the CR driven pulley assembly.
18. Affix the other side of the steel belt to the left side of the carriage.
19. Adjust the steel belt tension.
"7.4 Steel Belt Tension Adjustment" p.7-26
20. To reassemble the unit, reverse the removal procedure.
4.7.2
Replacing CR Motor Assembly
Do not touch the motor after continuous operation. You may get burned by the motor heated
up.
1. Remove the side maintenance cover R.
"4.2.4 Removing Side Maintenance Cover R" p.4-11
2. Remove the side top cover R.
"4.2.6 Removing Side Top Cover R" p.4-12
3. Remove the CR motor cable assembly.
Connect the white cable of the CR motor cable assembly to the side of the CR motor assembly where
the red seal is affixed.
The polarity of the CR motor assembly and CR motor cable assembly is as follows.
• Red seal: +
• White cable: +
• Black cable: -
Rev.-05
4-90
VJ-1604 Maintenance Manual