If an FC mezzanine card is installed in slot 1, at least one FC connection
●
blade must be installed in CB slot 2 of the system unit.
If a 1 Gb Ethernet mezzanine card is installed in slot 2 of a server blade, at
●
least one 1 Gb Ethernet connection blade must be installed in CB slot 3 or
in CB slot 4 of the system unit.
If a 10 Gb Ethernet mezzanine card or a 10Gb CNA mezzanine card is
●
installed in slot 2 of a server blade, at least one 10 Gb Ethernet connection
blade must be installed in CB slot 3 or in CB slot 4 of the system unit.
If an FC mezzanine card is installed in slot 2, at least one FC connection
●
blade must be installed in CB slot 3 or in CB slot 4 of the system unit.
If an Infiniband mezzanine card is installed in slot 2, an Infiniband connection
●
blade must be installed in CB slots 3 and 4 of the system unit.
If a SAS Expander mezzanine card is installed in slot 2, at least one SAS
●
connection blade must be installed in fabric 3.
You can install a combination of FC, Ethernet and Infiniband mezzanine
●
cards in a server blade. In this case, the Ethernet mezzanine card should be
installed in slot 1 and the FC or Infiniband mezzanine card in slot 2 of the
server blade.
BX920 S3
Upgrade and Maintenance Manual
Expansion cards and backup units
129