Connecting The Mains Power Supply - Ziton ZP1-F2 Installation Manual

Table of Contents

Advertisement

Chapter 2: Installation

Connecting the mains power supply

Note:
To avoid unwanted arcing, connect the mains power supply before
connecting the batteries.
The control panel can be operated at 110 V at 60 Hz or 230 V at 50 Hz
(+10%/−15%).
Mains power should be sourced directly from a separate circuit breaker in the
building electrical supply distribution board. This circuit should be clearly marked,
have a bipolar disconnect device, and only be used for fire detection equipment.
Feed all mains cables through the appropriate cable knockouts and connect
them to the fuse terminal block as shown in Figure 10 below.
Keep mains cables separate from other cabling to avoid potential short circuits
and interference. Always secure mains cables to the cabinet to prevent
movement.
Figure 10: Connecting the mains power supply
For fuse specifications, see Chapter 5 "Technical specifications" on page 77.
18
1. Mains fuse
2. Live
3. Earth
4. Neutral
ZP1-F Series Installation Manual