Polycom ATX Integrator's Guide
Integrator's Toolkit
Integration Sequence
1–2
You should have the following items available before you begin the
integration:
•
Calculator
•
Display cleaner (non-ammonia or non-alcohol-based)
•
Gray card, Lastolite
•
Laptop
•
Laser level, Stanley or equivalent
•
Latex gloves for handling displays and cameras
•
Level, 2-foot
•
Light meter, Minolta or equivalent
•
Marker, black permanent
•
Microfiber cloth
•
Tape, low tack
•
Tape measure
•
Wire cutters and strippers
•
Wire ties
When installing a Polycom ATX SDK or ATX 300 system, you usually install it
in the order listed below. Note, however, that the integration sequence may
vary due to factors such as room configuration, limited space to store the
equipment, number of installers, and so on.
Hardware:
Select the room
1
Select the displays and table
2
Determine the placement of the displays and tables
3
Install the displays and table
4
Install the cameras
5
Create the camera alignment marks
6
Place the chairs
7
Polycom, Inc.
Need help?
Do you have a question about the ATX 200 and is the answer not in the manual?
Questions and answers