To run a job, follow the simple procedure explained below.
Torchmate 5100

Running a Job

Datum:
When you first start the Visual Machine Designer and are connected to the
Accumove controller, the machine needs its motors powered on and MACHINE
ZERO position established. A message will appear stating PLEASE SWITCH DRIVES
ON. Release the E-STOP above the controller by turning is clockwise 1/4 turn, then
press the DRIVE ENABLE green button to power the motors. The machine can now
be datumed.
Open a Job:
Once MACHINE ZERO has been established, it is time to open a job and get it
prepared to cut. Press SELECT JOB and locate your file.
Set your Process:
In the PROCESS SETUP tab, enter in the material thickness and
amperage you are planning to cut. This will populate the CUT
PARAMETERS with the appropriate settings for the thickness/
amperage.
If using a different material thickness parameter than being
cut, the outcome will not be to specification.