Unit [n] > Calibration > Zero Pressure
This procedure evacuates the system and zeroes the pressure transducers. This calibration
should only be performed by qualified service personnel. In order to perform this procedure,
sample tubes must be attached to each port.
1. Install a blank sample tube or small plug on each applicable port.
2. Ensure that all applicable transducers are selected, then click Start. Click
cess is complete. The current pressure readings and operation status messages display.