CABLE TERMINATION
(3) The gap of the connector body and clamp nut is confirmed.
Tools
Note
Installation
Submission Prohibited
NEC Internal Use Only
(*) Gap: 2.2 to 2.7 mm
(*): Check Point
spanner (16 mm)
torque spanner (16 mm)
clearance gauge, measure
Do not remove the connector body tightened up once. When removing, it
is reworked from procedure 1 or a cable is exchanged.
6-31
NWD-107460-02E