a. Position a leveling pad underneath the leveling bolt.
b. Using an adjustable wrench, turn the leveling bolt clockwise to extend the bolt until the entire
weight of the rack rests on the leveling pad instead of the caster. The caster must be slightly off the
floor, so it can swivel slightly by hand.
Figure 13: Lowering an HPE rack leveling bolt
c. Lock the leveling pad in place by turning the locking nut counterclockwise until tight.
Figure 14: Tightening the locking nut on an HPE rack leveling bolt
d. Repeat for each leveling pad.

Installing the drives: Process overview

This process overview is for installing the drives.
If it is necessary to install additional drives, complete the following process:
Unpacking the factory-integrated-in-rack option: Process overview