2.5.4 Semi-Flush Mounting Bezel (Optional)

If semi-flush mounting of the ID50 Series Panel is
required, a recess 80mm deep and just large enough to
accommodate the back box must be cut in the wall (see
329
dimensions below).
375
383
453
To fit the bezel:
1 Before continuing, remove panel electronics and
2 Offer the bezel (A), flat sideways towards you, to the
E (x4)
E (x4)
3 With the bezel held in position, use the slotted holes
3
4 Secure the bezel using suitable M3 fixings. Ensure
5
Note: The ID50 Series Panel back box must be fixed to
5 Fit back box with attached bezel to the wall recess
3
14
All dimensions in millimetres
batteries (if fitted) - see Section 2.5, Dismantling the
Panel.
front of the back box (B) and position it so the bezel
front face (C) is lined up with the rear of the rounded
sides of the back box (D).
(E) on the bezel as guides and drill four appropriate
sized holes to fit M3 screws centrally in the slots.
Remove any swarf created.
the fixings are accessible from the outside of the back
box.
a solid vertical surface, or sub-frame inside the
recess, using its rear fixing holes. Do NOT rely on
the bezel as a means of fixing.
and assemble the panel, see Section 2.6.