Carry-Out Basic Commissioning - Siemens SINAMICS G120D Operating Instructions Manual

Control units, distrubuted converter
Hide thumbs Also See for SINAMICS G120D:
Table of Contents

Advertisement

5.5.4

Carry-out basic commissioning

Procedure
Proceed as follows to carry out basic commissioning:
1.
2.
3.
4.
5.
6.
7.
8.
Converter with control units CU240D-2
Operating Instructions, 04/2014, FW V4.7, A5E34262100B AA
Select the control mode.
See also Section: Selecting the control mode (Page 60)
Select the pre-assignment of the inverter interfaces.
The possible configurations can be found in sections: Factory settings of
the inputs and outputs (Page 46) and Default settings of inputs and
outputs (Page 47).
Select the application for the inverter:
Low overload for applications that only require a low dynamic
performance, e.g.: pumps or fans.
High overload for applications requiring a high dynamic performance,
e.g. conveyor systems.
Select your motor.
Enter the motor data according to the rating plate of your motor.
If you have selected a motor based on its order number, the data has
already been entered.
If you have set the "Vector control" control mode, then we recommend
setting "[1] Identify motor data at standstill and with motor rotating".
With this setting, the inverter
optimizes its speed controller.
If one of the following cases is applicable, select the setting "[2] Identify
motor data at standstill":
• You have selected "Vector control" as control mode; however, the
motor cannot freely rotate, e.g. for mechanically limited traversing
sections.
• You have set "V/f control" as control mode.
Set the most important parameters to suit your application.
We recommend the
setting "Calculate motor
data only".
5.5 Basic commissioning with STARTER
Commissioning
71

Advertisement

Table of Contents
loading

This manual is also suitable for:

Cu240d-2

Table of Contents