Installing a secondary full-height PCI riser cage option

When installed, this riser cage supports full-height, 3/4-length expansion boards up to 9.5". PCIe3 slot 2 is no
longer available.
Prerequisites
This option requires a dual processor configuration.
Before installing this option, be sure you have the following:
The components included with the hardware option kit
Any expansion boards or controllers you plan to install
Procedure
1.
Power down the server (Power down the server on page 24).
2.
Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
3.
Do one of the following:
a. Extend the server from the rack (Extend the server from the rack on page 24).
b. Remove the server from the rack (Remove the server from the rack on page 25).
4.
Remove the access panel (Remove the access panel on page 25).
5.
Remove the primary PCI riser cage (Removing the primary PCI riser cage on page 27).
6.
Remove the slot 2 bracket from the primary riser cage.
7.
If installed, remove the low-profile riser cage.