Test Run - Panasonic LJ-SK56A Installation Manual

Lithium-ion storage battery system
Hide thumbs Also See for LJ-SK56A:
Table of Contents

Advertisement

8. Test Run

8-1.Test Run
The following test runs are required before operating this system: the actual operation cannot be performed until test
runs have been completed.
• Stand-alone Operation Test
• Reverse Current CT Test
Test runs are required before the actual operation of the system. Actual operations cannot be performed until test
runs have been completed.
The work must be performed
8-2. Test Run Selection
Preparation
• Set the storage battery system to the stopped state in the normal state. The system can only be switched to the
parameter setting mode while it is in a stopped state.
Operation Procedure
Test Run Selection
Reverse Current CT Test
• Press "CLOCK(▲)"+"MENU(ENTER)" simultaneously for three seconds in the normal state to switch to the test run
selection prompt in the test run mode.
Stand-alone Operation test [TEST1] is displayed initially.
• Press "ON/OFF (CANCEL)" for one second in the test run selection prompt to return to the normal state.
• Press "CLOCK (▼)" or "DATA (▲)" in the test run selection prompt to switch between the
test [TEST1] and Reverse Current CT test [TEST2].
NOTICE:
If the destination setting is not set, TEST run operation is not possible (See 7-3).
If DRED setting is not to OFF, TEST run operation is not possible. (See 7-6)
by qualified personnel.
Stand-alone Operation Test
Normal State
Stopped (Grid-connected)
Stopped (Stand-alone)
3 sec
1 sec
Stand-alone Operation
93