Meeting Site Requirements
Evaluating and Meeting Cable Requirements
Meeting Power Requirements
Applicable Industry Standards
By carefully planning your site, you can maximize the performance of your existing network and ensure
that it is ready to migrate to future networking technologies.
The information in this chapter is intended for the system administrator, network equipment technician,
network manager, or facilities manager responsible for installing and managing the network hardware.
The chapter assumes a working knowledge of local area network (LAN) operations, and a familiarity
with communications protocols that are used on interconnected LANs.
Only qualified service personnel should install, maintain, or remove a switch, chassis, or its components.
Qualified service personnel have had appropriate technical training and experience that is necessary to
be aware of the hazards to which they are exposed when performing a task and of measures to
minimize the danger to themselves or other people.
Note
Before installing or removing any components of the system, or before carrying out any
maintenance procedures, read the safety information in
Planning Your Site
To install your equipment successfully, you should plan the site carefully. The site planning process has
three major parts:
1
Meeting site requirements.
The physical installation site must meet the following requirements for a safe and successful
installation:
Building and electrical code requirements
Environmental, safety, and thermal requirements for the equipment you plan to install
Equipment rack requirements
2 Evaluating and meeting cable requirements.
After examining your physical site and verifying that all environment requirements are met, evaluate
and compare your existing cable plant with the requirements of the Extreme Networks equipment
to determine if you need to install new cables.
3 Meeting power requirements.
Summit Family Hardware Installation Guide
Technical Specifications
of this guide.