CONTAINERIZED KITCHEN (CK)
OPERATION UNDER USUAL CONDITIONS
Fabric Erection – Food Preparation Wing
The wing floor must be level with the center core floor to ensure a
correct fit for the roof arches.
1. Unstrap the two refrigerators, unlock their casters, and move them into the serving wing to
allow access to the food preparation wing. When moving a refrigerator, grasp the metal
bracket on the back. Do not pull on the tube on the back of each unit.
2. Assemble a roof arch and an "X" vertical as shown in Figure 6.
3. Position one or more personnel in the middle of wing to push up the fabric cover and
support it by hand.
4. Move onto the wing while holding the arch frame assembly.
5. Starting with the center interior arch location, with other personnel supporting the fabric,
rotate the arch frame assembly to insert the upper end of the arch into the arch cup at the
header, as shown in Figure 7.
6. Pushing lightly on the end of the assembly to hold it in the header cup, swing the assembly
(keeping corner below fabric cover) until the vertical bottom end is inserted into the arch cup
at the floor.
7. Rotate the assembly into vertical position. Some force is required once the arch contacts
the fabric. Other personnel may release the fabric to help. Once in place, release the arch.
8. Repeat steps 5 through 7 for the other two central cup locations with roof arch/"X" vertical
assemblies.
9. Repeat steps 5 through 7 for the two corner locations using a roof arch and a "T" vertical.
10. Starting at the corner nearest the mechanical room, install two arch spacers, as shown in
Figure 8, between the first two sets of adjacent arches. Slide an arch away then back to
push stub inside spacer.
11. At the opposite corner, install an arch spacer between the first two arches.
Be careful not to pinch your fingers while installing the adjustable spacer.
12. Install the adjustable spacer, as shown in Figure 10, in the remaining location. Slide the
adjustable spacer between the stubs of the verticals. To obtain the correct tension, adjust
the length by moving the bolt to the desired location. Orient the spacer so that it will tighten
by pushing outward. Two personnel may be needed to straighten the spacer.
13. Apply tension to the spacer by pushing it outward to straighten. Slide the sliding tube to
lock.
TM 10-7360-226-13&P
NOTE
The stubs on the verticals must face toward the inside.