CHAPTER 6
Site Preparation
Site Preparation Checklist for an EX4600 Switch
Table 11: Site Preparation Checklist
Item or Task
Environment
Verify that environmental factors such as
temperature and humidity do not exceed
switch tolerances.
Power
Measure the distance between external power
sources and switch installation site.
Calculate the power consumption and
requirements.
Rack or Cabinet
Verify that your rack or cabinet meets the
minimum requirements for the installation of
the switch.
Plan rack or cabinet location, including required
space clearances.
Copyright © 2014, Juniper Networks, Inc.
Site Preparation Checklist for an EX4600 Switch on page 31
The checklist in
preparing a site for EX4600 switch installation.
For More Information
"AC Power Specifications for an
"Rack Requirements for an EX4600
summarizes the tasks you need to perform when
Performed By
Date
31