3.2

Rack Enclosure Installation

CAUTION
CORRECT GROUNDING PROTECTION IS REQUIRED – Connect the ground
stud, located on the rear panel of the unit, to a power system that has
separate ground, line and neutral conductors. Do not operate the unit without
a direct connection to ground.
The rack must be connected to a suitable earthing connection at all times.
You must connect the rack ground bar to a suitable earthing demarcation
point.
CORRECT AIR VENTILATION IS REQUIRED – Air flow must not be impeded.
Make sure there is proper air ventilation. Do not block the top of the rack or
the presence of a rack blower. The air temperature inside the rack must never
exceed 50°C (122°F).
If there is any doubt, contact Comtech EF Data Product Support during
normal business hours.
Install the unit in its assigned position in a rack enclosure (Figure 3-2). You must install the rack in
a location with a controlled environment. Failure to obey this requirement can cause damage to
the equipment, and denial of subsequent warranty claims. You may use:
A standard rack-mounted shelf
User-supplied screws to secure the front panel to the rack enclosure threaded front
mounting rails
CEFD's optional KT/6228-2 (4") or KT/6228-3 (10") Rear Support Brackets Kit
(Figure 3-3).
CEFD's optional 22" (FP/SL0007), 24" (FP/SL0008) or 26" (FP/SL0006) Side-Mounting
Rack Slide Set (Figure 3-4).
For information about custom rack enclosures, contact CEFD Product Support.
Installation and Startup
LBC-4000 L-Band Up/Down Converter System