26
Configuring the Hardware in the Rack
Configuring the Hardware in the
Rack
After you have installed all the hardware in the rack, you must configure the components and
connect them together.
This section covers the following tasks:
•
''Configure Media Server 1'' on page 27
''Connect Duplication Cables'' on page 43
•
''Configure Media Server 2'' on page 43
•
•
''Connect UPS Ethernet Cables to Ethernet Switch'' on page 50
''Configure the UPSs'' on page 51
•
•
''Configure the Avaya Ethernet Switch (if used)'' on page 55
Once the hardware is installed you must upgrade the software on the two media servers,
configure them, install the license and Avaya authentication files, and test the connectivity to
the customer's LAN. You upgrade and configure the first media server, verify its operation, then
upgrade and configure the second media server and verify its operation.
October 2002