Configuring the UPS for EBMs

To ensure maximum battery runtime, configure the UPS for the correct
number of EBMs:
1.
2.
3.
4.

Initiating the Battery Test

NOTE The batteries must be fully charged and the UPS must not be in Battery mode to
perform the battery test.
NOTE For an accurate battery test, test the UPS with at least 10% load applied to the UPS.
You can configure the battery test settings, initiate a test, cancel a test,
and view the test report.
Configuring the Battery Test. The UPS automatically performs a battery
test every 7 to 90 days (user selectable) if this option is enabled. To
enable or disable the automatic battery test and to select the test
frequency and length, select MENU from the system status screen,
then select SETUP, USER SETUP, and BATTERY TEST. Select to enable
or disable the automatic test, choose a test period (7 to 90 days), and
choose the test time (1 to 99 minutes).
®
EATON Powerware
9140 UPS (7.5–10 kVA) User's Guide
Select MENU from the system status screen, then select SETUP,
USER SETUP, and BATTERY PACK.
Use the
or
button to select the number of battery packs in
your UPS configuration:
All UPS and EBM Cabinets
UPS + 1 EBM
UPS + 2 EBMs
UPS + 3 EBMs
UPS + 4 EBMs
Press the
button to save the setting.
Press the
button until the system status screen appears.
S
164201622 Rev A FINAL DRAFT 14-Jul-2006
OPERATION
Number of Battery Packs
2
3
4