6.2

Switch on charging station

Risk of electric shock when moist due to condensed water
Before putting the charging station into operation, an authorized and qualified electrician
must check whether there is any moisture in the charging station. Manually remove even
small amounts of condensation before commissioning. Take appropriate measures for
drying.
Do not switch off the power supply for an extended period of time after commissioning. This
will prevent condensation in the charging station.
Automatic starting of the charging station
The charging station starts automatically. A progress display in percent is shown on the
display when the charging station is booting or updating. Wait for the charging station to
fully start up. This may take several minutes. The LED strips light up white initially during
startup. In ready-to-operate state, the LED strips are lit green and the display shows the start
menu.
Figure 6-1  Start menu
NOTE
In standby, the unloaded EMC filters generate capacitive reactive power. This is compensated
as soon as a vehicle is charged with DC. Then the charging station consumes almost
exclusively active power.
SICHARGE D
Operating Instructions, 11/2023, A5E50556539-AG
DANGER
Commissioning
6.2 Switch on charging station
107