Load Sensing System

5.3-3 Calibration of Load Sensing System

NOTE
There is a time-out period of 10 minutes for
each step in the calibration process (indicated
by a solid green light). Should you exceed 10
minutes, the calibration process must be started
over from the beginning.
Preparation
1. Ensure the MEWP is on firm, level ground.
2. Fully retract
and lower
3. Turn the engine off
4. Pull out both emergency stop buttons
Result: The overload indicator light and audible alarm pulse two times.
5. Make sure the platform is unloaded and is free from any surface contact. Remove all options from the
platform.
6. Open the base control box door, and locate the dual capacity module on the inside right wall of the control
box.
SJ85 AJ
the boom.
.
and the flip the engine enable switch to the on position .
Red
Yellow
Actuator Button
Section 5 – Procedures
Green
229044ADA
157