15. Connect each power cord to the server.
16. Connect each power cord to the power source.
17. Power up the server.
The installation is complete.
Installing the chassis intrusion detection switch
Prerequisites
Before you perform this procedure, make sure that you have the following items available:
The components included with the hardware option kit
Procedure
1.
Power down the server.
2.
Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
3.
Do one of the following:
•
Extend the server from the rack.
•
Remove the server from the rack.
4.
Remove the access panel.
5.
Install the chassis intrusion detection switch.
6.
Install the access panel.
Hardware options installation