Cladding Panels Fitting - Access 7000 Installation Manual

Table of Contents

Advertisement

Door blocking cable

5.9 CLADDING PANELS FITTING

WARNING
When running the platform before the middle cladding panels are finished there is a
risk that the platform and/or the flat cable clings on to the cladding supports, shaft- or
cladding panels.
• Assemble the first pair of cladding support beams in the pair of track shoe bolts.
• Adjust the height using the track shoe bolts. The cladding support beams are to hang approximately
10 mm under the mast top.
Note:
Do not tighten the track shoe bolts in this stage, wait until after adjustments
have been made.
Picture below shows the door blocking cable,
plug 1 goes to next door, plug 2 coming from pre-
vious door or electric cabinet and plug 3 goes to
door blocking contact
7000 100 en-GB AD
ASSEMBLY
77