Make the screw joint by:
• Thread together the screw until the marking
is in the same level, position.
• Use two pipe-wrenches to finally tighten the
screw joint until the holes for the spring pins
are in correct position. Use cardboard
guards, or something similar, on the screw
to protect from damaging the thread.
• Hammer in the spring pins (2 pcs) SF-SSS
N8x30 with a 8 mm mandrel.
• Control that the spring pins does not stick
out on either side.
• Control and adjust that the screw is free
from damage. If needed smoothen uneven
surfaces around the joint and around the
spring pins with a file. We recommend that
you use a file according to illustration below.
It is better to file down more than less.

6.3.3 NUT PACKAGE

Before installation control the following:
Control that the nut package is clean and that the safety and main nut is in the right position. The mark-
ing on the nuts shall be in line vertically, see illustration below
1
Install the screws into the nut package by:
• Loosen the transport screw pos 1 a couple
of turns.
• Put the screw in place and turn it approxi-
mately 5 turns down until it is in position in
the main nut.
Fig. 121 Use Pipe wrenches to tighten the screw
Fig. 122 File
Fig. 123 Safety nut in right position