RECEIPT OF MATERIAL ON SITE
• Tensiometer for belt tension
• Applicable drawing and circuit diagrams for the order.
For more detailed information regarding installation tool recommendations, see separate document.

3.2 SITE SURVEY

Confirm:
• that the installation site corresponds to approved drawing
• that the length of the mast is correct, depends on door configuration. - Full size door - Length from
top level floor to top of the mast, min 1055 mm - Half size door - Length from top level floor to top
of the mast, 1070±15 mm
• that the travel and top height corresponds to approved drawing
• that the pit corresponds with approved drawing
• that the hole through floor/pit plumb for lift corresponds to approved drawing
• that it is possible to fix door and structure
• that all floor levels are finished before installation
• that a bar in ceiling is in place. SWL 500 kg
• that there is lighting that provides 50 lux a the floor level in the shaft, in front of every door and out-
side the electrical cabinet
• that the supporting walls in the shaft are dust sealed
• that the shaft is cleaned out
• that the pit is painted with oil resistant paint
• that main electrical supply is provided at the electrical cabinet
• that there is a two way communication line provided
• that the power outlet is available near the lift
• that national rules and regulations for such an installation are not being contravened
For outdoor lifts, confirm:
• that the pit has an abundant floor drain (for rain water)
• that there is external 230 V supply (for ventilation /heating fan)

3.3 LIFTING POINTS

A lifting point/hook must be provided centrally to the shaft with a certified load of 500 kg SWL. The lift-
ing point (see pos 1) is illustrated in Fig. 2 Lifting point.