Unpacking; Material Preparations - Access 7000 Installation Manual

Table of Contents

Advertisement

Tripping hazard over cables etc.
Hazard of bulky parts tipping over

3.7 UNPACKING

The platform lift is normally delivered in two pallets with several parts.
The two pallets consist of:
Pallet one
• Mast
• Shaft parts
• Box with installation material and packing check list for pallet one
Pallet two
• Platform
• Doors**
• Wall panel
• Box with installation material and packing check list for pallet two
* If the lift has more than 3 stops and a long travel, the doors will be packed on a third pallet.
Pallet three*
• Doors

3.8 MATERIAL PREPARATIONS

• Remove the cover panels, safety edge and safety frame from the platform before moving it into the
building to avoid damage to the platform.
RECEIPT OF MATERIAL ON SITE
7000 100 en-GB AD
11