Prepare the Power Cords

Prepare the Power Cords
Prepare the power cords by routing them from the AC power source to the server.
Caution -
to a serial terminal or a terminal emulator (PC or workstation). The server goes into Standby
mode and Oracle ILOM on the SP initializes as soon as a power cable connects a power supply
to an external power source. System messages might be lost after 60 seconds if a terminal or
terminal emulator is not connected to the SER MGT port before power is applied.
Note -
it will be a nonredundant condition. Do not be concerned with this fault in this situation.
Route the power cords from the AC power source to the rear of the server.
1.
Do not attach the power cords to the power supplies at this time.
2.
Connect a device to the SER MGT port.
76
SPARC S7-2L Server Installation Guide • June 2017
Do not attach power cables to the power supplies until you have connected the server
Oracle ILOM signals a fault if both power supplies are not cabled at the same time, since