Verify Operation of Slide Rails and CMA
Two people are recommended for this procedure, one to move the server in and out of
Note -
the rack, and one to observe the cables and CMA.
1.
Slowly pull the server out of the rack until the slide rails reach their stops.
2.
Inspect the attached cables for any binding or kinks.
3.
Verify that the CMA extends fully from the slide rails.
4.
Push the server back into the rack.
Verify Operation of Slide Rails and CMA
Installing the Server
55