(1) Pre-fab. module base
The minimum cross-sectional area of a concrete platform must be 2900 mm x 1000 mm. The
concrete platforms must be 200 mm higher than the ground to ensure efficient drainage.

2.3 Power Supply and Distribution Requirements

Issue 03 (2020-06-09)
Figure 2-2 Base installation scenario diagram (unit: mm)
Load-bearing capacity of concrete platforms: meets the requirements of the maximum
weight of a pre-fab. module 25,000 kg and NEBS Zone 3 antiseismic requirements.
Recommended load-bearing capacity calculation: Maximum weight of a pre-fab. module 25,000 kg x 3
(NEBS Zone 3 requires amplitude acceleration 3G) x 1.5 (0.5 times the engineering construction error
and margin)/Effective support contact area (The effective contact area in the concrete platform
installation scenario is 4 x 1700 cm
The horizontal error between concrete platforms must be less than 10 mm.
Concrete pads or passages with the load-bearing capacity meeting local civil work
standards can be built on the site outside the concrete platforms for access and servicing.
The power supply for the FusionModule1000 can be the mains or a diesel generator
(DG). For the detailed input routes and capacity, see the power supply and distribution
system diagram for the solution in use.
Copyright © Huawei Technologies Co., Ltd.
(2) Concrete platform
2
.)
2 Site Requirements
(3) Ground
4

Advertisement

Table of Contents
loading

Table of Contents