Huawei FusionModule1000A Installation Manual page 67

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A:
Table of Contents

Advertisement

FusionModule1000A40 Prefabricated All-in-One Data
Center
Installation Guide
After routing the 4G antenna cable into the pre-fab. module through its ELV feeder
window (No. 11), seal the port in the feeder window using sealing putty.
The cable outside the pre-fab. module must be fit with a corrugated metal hose.
The cable outside the pre-fab. module can be bent only in the U-shape.
8.
When removing the sealing plate from the suspended ceiling, assign one person to remove the
screws while the other holds the sealing plate. Pay attention not to damage the light inside the
ceiling plate.
Issue 03 (2020-06-09)
Figure 8-12 Installing the 4G antenna
Remove the three plastic sealing rings from the sealing plate screws holes in the
suspended ceiling, and loosen the four M4 captive screws securing the sealing plate.
Copyright © Huawei Technologies Co., Ltd.
8 Installing Devices Inside Pre-fab. Modules
60