9

9.1 Connecting Input Power Cables for Pre-fab. Modules

Prerequisites
Pre-fab. modules and external cable trays have been installed.
Preparations
Tools: crimping tool, Phillips screwdriver, adjustable wrench, cable cutter, heat gun
Materials: cable tie, cable, terminal, heat shrink tubing
Skill requirement: skilled technician
Procedure
Step 1 Open the door of the power PDB.
Step 2 Remove the plugs from the two cable holes at the bottom of the power PDB.
Figure 9-1 Removing the plugs from the cable holes
Issue 03 (2020-06-09)
Installing Cables Outside Pre-fab.
Copyright © Huawei Technologies Co., Ltd.

9 Installing Cables Outside Pre-fab. Modules

Modules
75