Huawei FusionModule1000A Installation Manual page 26

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A:
Table of Contents

Advertisement

FusionModule1000A40 Prefabricated All-in-One Data
Center
Installation Guide
Mark all four mounting holes where each angle steel bracket contacts the concrete
platform.
Place a wooden block on the top of an expansion bolt, and then knock at the wooden block
using a claw hammer to avoid damaging the expansion bolt.
When you drill a hole using a hammer drill, keep the drill bit perpendicular to the ground
and hold the drill stock firmly with both hands to prevent irregular drilling and damage to
the ground.
If the ground is too hard and smooth for the drill bit to secure its position, use a chisel to
punch a pit before drilling.
Before you hammer an expansion bolt vertically into a mounting hole, clean up dust from
the inside and surrounding of the hole.
Each angle steel bracket must be secured by two mounting holes. Preferentially drill the
outer two mounting holes. If steel bars in a concrete platform block the drill bit, drill the
inner mounting holes.
3.
Issue 03 (2020-06-09)
Figure 4-3 Determining mounting holes for an angle steel bracket
Install expansion bolts.
a.
Drill mounting holes using a hammer drill.
b.
Rotate nuts onto expansion sleeves to prevent the expansion sleeves from fluttering.
c.
Knock the expansion bolts vertically into mounting holes until the flat washers are
flush with the floor.
d.
Remove the nuts, spring washers, and flat washers.
Copyright © Huawei Technologies Co., Ltd.
4 Installing Pre-fab. Modules
19

Advertisement

Table of Contents
loading

Table of Contents