Huawei FusionModule1000A Installation Manual page 49

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A:
Table of Contents

Advertisement

FusionModule1000A40 Prefabricated All-in-One Data
Center
Installation Guide
Figure 6-2 Installing pipes
(1) Water refill pipe
1.
2.
3.
Step 4 After the hot-melt connection, wrap the exposed part of the water pipe with 10 mm thick
thermal insulation foam.
----End
Follow-up Procedure
Verify that the pipe connector is closely melted with the pipes at both ends.
Issue 03 (2020-06-09)
Remove the tinfoil on the plug of the water refill valve.
Connect the PP-R pipe connector to the pipes on both ends using a hot melt device.
Install the other pipes in the same way.
Copyright © Huawei Technologies Co., Ltd.
6 Installing External Pipes for Smart Cooling Products
(2) Drainpipe