Procedure
Step 1 Connect the generator start/stop cables to the terminals on the XT2 terminal block.
Table 9-1 Generator start/stop cable connection
Cable Connecting Position in the Device
Generator start/stop
Issue 03 (2020-06-09)
Here connecting one of the cables is used as an example. XT2-6 is a normally open contact, XT2-7 is a
common contact, and XT2-8 is a normally closed contact.
Copyright © Huawei Technologies Co., Ltd.
9 Installing Cables Outside Pre-fab. Modules
Generator Start
Generator Com
Generator Stop
Cable Connecting
Position in the UPS
XT2-6
XT2-7
XT2-8